From 2001 - 2004 I was responsible of projecting 4 big biogas facilities in Denmark. The Company Green Farm Energy builded 4 big facilities and the first was Over Løjstrup Biogasanlæg.
I had the projecting responsibility of all 4 facilities at the same time. All constructions, tenders, quotations,calculations, drawings, diagrams, function descriptions were performed in my department with 20 employees.
Project sizes 60-70 mio. dkk.
Energy / power production 2 MW continuously